What the client required
We have just completed a school refurbishment to 5 classrooms, the staff room corridor’s and replacement of doors over the summer holidays. We had 5 weeks to complete all works, however following asbestos being found, this meant that there would be over a week delay in our programme.
We have just completed a school refurbishment to 5 classrooms, the staff room corridor’s and replacement of doors over the summer holidays. We had 5 weeks to complete all works, however following asbestos being found, this meant that there would be over a week delay in our programme.
It was very important for our customer that the school be open as planned, so we supplied a further 2 operatives and worked extended hours and weekends to ensure we met with our customer’s urgent needs.
Our client was over the moon with the extra help we provided and we continue to maintain a happy working relationship with them.